INSTANT PRESS ADVISORY

on Behalf of New England Coalition  

 

NRC has denied Entergy Nuclear Operation’s (ENO) bid to cancel parent company decommissioning fund guarantees for Vermont Yankee Nuclear Power Station. ENO claimed in its April “Notice of Cancelation” that because NRC had issued a renewed license, twenty years of operation would allow interest on invested decommissioning funds to build a surplus, obviating the need for a forty million dollar guarantee. NRC Staff denied the cancelation stating that Vermont’s decision to withhold state permission renders another 20 years of operation at best uncertain. ENO is invited to file another Notice of Cancellation when the matter is settled in the courts. “In the meantime” said New England Coalition advisor, Raymond Shadis, “It looks like, put up and shutdown.”

 

 This I believe is the first federal acknowledgement that Entergy’s Vermont Yankee is still on track for shutdown in March 2012, just eight months from now. 

 

If VY goes into so-called, Safstor, that is monitored storage and delayed decommissioning, the bulk of decommissioning funds may remain invested and growing during that period, he said. The minimum available as required by NRC, is to take care of radiological decommissioning.  Decommissioning to non –radiological greenfield standards as required by Vermont is not in NRC’s purview. Originally, the VY decommissioning fund was built through a tariff paid by ratepayers and supplemented by Vermont Yankee Nuclear Power Corporation. Since Entergy bought the plant in 2002, the company has contributed nothing to the fund; relying entirely on investment returns to fund its growth.

 

To my best knowledge Entergy Nuclear Operations DID NOT Inform the Vermont Public Service Board of its intention to file a notice of cancellation of parent company guarantee of decommissioning funds; adequacy and security of decommissioning funds being a matter before the Board in Docket 7440 (the extended operation CPG case) and Docket 7600 (the aging piping/groundwater contamination case).

 

Raymond Shadis

207-882-7801

 

New England Coalition

802-257-0336

+++++++++++++++++++++++++++++++++++++++

 

UNITED STATES

NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

 

August 10, 2011

 

Site Vice President

Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station

 

P.O. Box 250

Governor Hunt Road

Vernon, VT 05354

 

SUBJECT: NRC RESPONSE TO NOTICE OF CANCELLATION OF PARENT

GUARANTEE FOR VERMONT YANKEE NUCLEAR POWER STATION (TAC NO. ME6674)

 

Dear Sir or Madam:

 

On April 29, 2011, Entergy Nuclear Operations, Inc. (ENO) submitted to the U.S. Nuclear

Regulatory Commission (NRC) a notice that Entergy Corporation intends to cancel a parent company guarantee by Entergy Corporation guaranteeing $40 million of the decommissioning cost for the Vermont Yankee Nuclear Power Station (Vermont Yankee) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 111250255). In the submittal, ENO states that because the NRC notified the licensees that Vermont Yankee's facility operating licensee has been renewed for a 20-year term, now set to expire at midnight on March 21,2032, Entergy Corporation no longer needs to provide a parent company guarantee for Vermont Yankee, due to the anticipated earnings of the decommissioning funds during the renewal period.

 

In its submittal, ENO referenced its decommissioning funding status report on March 31, 2011, which, according to its calculation, provided approximately $211 million in surplus funds over the NRC's minimum funding amount without consideration of the parent guarantee, rendering the existing parent company guarantee for additional financial assurance no longer necessary. Also according to the submittal, Paragraph 13 of the parent company guarantee and Title 10 of the Code of Federal Regulations Part 30 Appendix A(III)(A), states that the parent company guarantee will remain in force unless the guarantor sends notice of cancellation and the cancellation may not occur during the 120 days beginning on the date of receipt of the notice of cancellation by both the licensee and the Commission. Therefore, ENO notified the NRC that Vermont Yankee no longer required a parent company guarantee and that Entergy Corporation was intending to remove the parent company guarantee 120 days from the receipt of the notice.

 

The NRC staff has reviewed the notice of cancellation by ENO and has determined that external factors may affect the licensee's decommissioning financial assurance. The reason for the NRC staff's decision is based on the ongoing civil court case Entergy Nuclear Vermont Yankee v. Shumlin, No. 11-cv-99 (D.V.T filed April 8, 2011) (VY v. Shumlin). Also, on June 23, 2011, the State of Vermont Department of Public Service submitted a letter to the NRC stating that Vermont is currently reviewing land use, power needs, alternatives, costs, economic impacts and reliability for any generation source and has not determined that Vermont Yankee meets

-2-

 

 

the State criteria for continued operation (ADAMS Accession No. ML 11187 A311). Depending

on the outcome of Vermont's review and VY v. Shumlin, Vermont Yankee may no longer

operate after March 21, 2012. Under that condition, the anticipated earnings during the renewal

period would not be realized. Because of the uncertainty surrounding the plant's future,

cancellation of the guarantee at this time would be premature.

 

If the parent company guarantee is cancelled, the licensee will be required to provide adequate financial assurance within 90 days of receipt of the notice of cancellation. However, when the issues raised by Vermont and in the litigation are resolved, END may resubmit notice of its intent to remove the parent company guarantee for an expedited review by the NRC staff.

 

If you have any questions regarding this letter, please contact me at 301-415-4125.

 

Sincerely,

 

James Kim, Project Manager

Plant Licensing Branch 1-1

Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation

 

Docket No. 50-271

 

cc: Distribution via Listserv

 


 

-2

 

 

the State criteria for continued operation (ADAMS Accession No. ML 11187A311). Depending

on the outcome of Vermont's review and VY v. Shumlin, Vermont Yankee may no longer

operate after March 21, 2012. Under that condition, the anticipated earnings during the renewal

period would not be realized. Because of the uncertainty surrounding the plant's future,

cancellation of the guarantee at this time would be premature.

 

If the parent company guarantee is cancelled, the licensee will be required to provide adequate

financial assurance within 90 days of receipt of the notice of cancellation. However, when the

issues raised by Vermont and in the litigation are resolved, ENO may resubmit notice of its

intent to remove the parent company guarantee for an expedited review by the NRC staff.

 

If you have any questions regarding this letter, please contact me at 301-415-4125.

 

Sincerely,

 

Ira!

 

James Kim, Project Manager

Plant licensing Branch 1-1

Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation

 

Docket No. 50-271

 

cc: Distribution via Listserv

 

DISTRIBUTION:

PUBLIC RidsNrrDorlLpl1-1 Resource RidsOgcMailCenter Resource

RidsNrrLASLittie RidsNrrDprPfib Resource RidsNrrPMVermontYankee

ASzabo RidsRgn1 MailCenter RidsNrrDorlDpr Resource

RBellamy, R1 RidsAcrsAcnw_MailCenter Resource

 

ADAMS Accession N0.: ML 112210193 *See memo dated August 5, 2011

 

a e

 

OFFICE LPL 1-1/PM LPL1-1/LA PFIB/BC LPL1-1/BC

NAME JKim SLittie CRegan* NSalgado (RGuzman for)

!,ATE 8/10/11 8/10/11 8/512011 8110/11

 

OFFICIAL RECORD COpy

 

 

This announcement was sent by New England Coalition (NEC). If you wish to update your email address or to be removed from our private email list please  email us at necnp@necnp.org  or call us at 802-257-0336. Thank you.

 

NEC, organized and founded in 1971, is the region’s sole advocate for environmental and nuclear safety with intervenor status in the Entergy Vermont Yankee federal relicensing process, and is an intervenor in two open dockets before the Vermont Public Service Board Docket 7440 – Shall Entergy Nuclear Vermont Yankee receive a CPG for an additional 20 years of operation and less widely reported Docket 7600 which resulted from an action brought by Conservation Law Foundation regarding the tritium leaks at VY.

 

New England Coalition is a 501(c)(3) non-profit organization. All contributions are tax-deductible.  Donate at necnp.org using PayPal or send a check to NEC, PO Box 545, Brattleboro , VT 05302   www.necnp.org