|
NEWS RELEASE RELEASE DATE Feb 2, 2010 1:55 PM
Contact: Ray Shadis - Consultant 207-882-7801 NEC
will be filing a 10 CFR 2.206 Enforcement Petition today requesting that NRC
undertake a number of enforcement actions in response to: (1)
growing concentrations of
radio-contaminants in the soil and groundwater at VY, (2)
Entergy’s failure to know and
understand Vermont Yankee’s design, layout, and construction, (3)
the obvious inadequacy of Entergy VY’s
underground piping aging management plan as presented and approved in ENVY’s License
Renewal Amendment application, (4) the agency’s failure to catch on until the
situation became grossly self revealing.
Why this
call for a shutdown now? And not a week ago before the VT Public
Service Board? A continued increase in concentrations for this period of time
is more indicative of a plant system leak, rather than diminishing
concentrations which would be more indicative of the dispersal of some pool
or reservoir left from some past contamination incident. Shutdown would
permit isolation of various plant systems and thus the leak. NRC is the
only agency with authority to order a shutdown, or indeed any action, with
respect to nuclear safety. Right issue. Right reasons. Right Time.
Right
venue.
Ray
Shadis for THIS RELEASE AND ADDITIONAL FILINGS WILL BE POSTED AT www.NECNP.org _______________________________________________________________________ New England Coalition seeks
to close VY 02-02-2010
"Because the rate of contamination appears to be
increasing, they need to cease operations until they determine the source,"
said Ray Shadis, NEC’s technical consultant. Entergy has applied to the Nuclear Regulatory Commission
to extend the operating license of Yankee for another 20 years, from 2012 to
2032. In addition to NRC approval, Entergy must also receive a certificate of
public good from the Public Service Board and the OK from the Vermont
Legislature. The Legislature and the PSB were on track to decide
whether Yankee should be allowed to continue to operate when a tritium leak
discovered on Jan. 7 derailed the process. When the state was notified about the leak, regulators
learned that Entergy didn’t reveal the extent of buried piping at the power
plant during public hearings before the Public Service Board last year. During a status conference last week with the PSB, Entergy
was ordered to go back and review every single page of testimony presented to
it to identify any other areas where Entergy might have left out important
information. "It’s a start," said Shadis. Entergy is scheduled to return to the PSB next week to let
it know how long the review could take. "It may or may not be that they intended to mislead,
but what they did shows great disrespect for the
process by trying to blow past these questions," said Shadis. In the five or six proceedings in which NEC has been a
part, "In every instance their answers were coy and evasive," he
said. While it may be OK to not offer information that has not
been asked for in a criminal trial, said Shadis, it’s not OK "when an
applicant is asking for the state’s goodwill for a permit. They act like
defendants instead of applicants." Information that Entergy has turned over so far "is
not helpful," he said. A list of buried pipes submitted by Entergy was nearly
illegible, said Shadis, and had no description of the piping systems except
for engineering codes with no legend to explain what
those codes were. "If this is the way it’s going to be, we will be
bumping heads soon," he said. The state also needs to investigate how the tritium leak
could affect decommissioning costs, said Shadis. Rough calculations indicate cleaning up the tritium leak
could add as much as $113 million to the costs of decommissioning the power
plant when it closes, said Shadis. "They have to go back to the drawing board,"
said Shadis. "We need them to do a thorough site survey." Bob Audette can be reached at raudette@reformer.com, or at
802-254-2311, ext. 273. This email was sent to «EMAIL» at NECNP@NECNP.ORG. If you no longer wish to receive correspondence or have an alternate member in your organization who should receive this news release simply write us at necnp@necnp.org or call the office at 802-257-0336 and ask us to update our mailing list. |