BRATTLEBORO — Neglected maintenance on the brakes on
a Vermont Yankee refueling floor crane failed in May as
it was holding a cask full of spent nuclear fuel because
Entergy Nuclear failed to correct ongoing problems with
the crane, a recently released inspection report from
the Nuclear Regulatory Commission stated.
The
crane has accumulated seven problems in more than three
years, a result of "Entergy's failure to take timely and
appropriate corrective action," the special inspection
report stated.
"As a result, the brakes failed to
function during the movement of a spent fuel storage
cask," on May 12, the report stated.
In addition
to the neglected maintenance of the crane's brakes,
Entergy reported that it had also violated federal
regulations when it removed mechanical safety stops on
the crane on June 10 while spent fuel was being moved,
according to reports on file with the
NRC.
Federal regulations "requires crane travel
limit mechanical stops to be installed during cask
handling operations to prohibit movement of the cask
over irradiated fuel," according to the
report.
At the time of both incidents, Entergy
Nuclear was moving high-level radioactive waste into a
steel and concrete "dry cask," and had moved the cask
out of the spent fuel pool," according to a report filed
by Entergy Nuclear on July 31.
The two incidents
come as Vermont Yankee starts using its dry-cask storage
facility. The plant ran out of storage inside the
reactor building this year, and it would have been
forced to shut down without the new facility, which was
built just north of the plant.
The company said
its own inspectors discovered the missing mechanical
stops on June 10, Entergy Nuclear spokesman Rob Williams
said.
He said Entergy Nuclear procedure was in
conflict with federal regulations, since the Entergy
procedure allowed the supervisor on the floor to remove
the stops.
He said the problem was reported to
the NRC within the 60-day time limit. He said the NRC
was notified verbally on June 10.
"Subsequently,
VY determined … that the stops were removed and
reinstalled (and) did not comply with the requirements
of the TS (technical specifications,)" the company wrote
to the NRC.
Despite the missing safety equipment,
the company said there were no personnel or public
safety implications.
Williams said that five
casks were filled with old irradiated fuel, and that the
procedure, which started on May 12, was completed on
July 29.
The NRC, in an Aug. 5 inspection report
on the original May 12 incident, said the crane brake
problem only warranted a "green" finding, the lowest
level finding, since it didn't result in any direct
safety problem.
The crane operator had put on the
brakes to stop the cask while it was 4 inches above the
floor, but the cask sunk slowly to the floor
instead.
The NRC report said the brakes failed
because of faulty relays.
Raymond Shadis, senior
technical advisor for the nuclear watchdog group New
England Coalition, said the crane brake failure, and the
missing stops, were cause for worry.
"They were
in violation of their tech specs," he said. "Those stops
are there to provide a margin of safety and they
eliminated one of the safety steps."
Shadis also
noted that an Entergy top-level official had reassured
the public immediately after the May 12 incident that
there were mechanical stops in place to keep the crane
from dropping the cask back into the fuel pool, on top
of the radioactive fuel.
If the cask had slipped
into the pool it could have crushed the spent fuel
assemblies, or even punctured the bottom of the fuel
pool, he said.
He noted that Entergy had sat on
the information for two months before notifying the NRC
formally on July 31.
"It's typical of the way
they handle uncomfortable information," he
said.
The company blamed the problem on
"inadequate procedures."
The federal inspectors
said the crane that was involved in the May 12 incident
had had a total of seven problems in recent years, and
that Entergy had failed to follow through on corrective
measures it had promised to do.
"The inspectors
determined that Entergy failed to take appropriate
corrective actions when system performance goals were
not met, prior to moving spent fuel," according to the
NRC report.
The Aug. 5 inspection report did not
make mention of the second problem with the
crane.
The supplemental report from Entergy
Nuclear had been filed on July 31.
Entergy
Nuclear safety assurance director John Dreyfuss, in
statements to the press in May, said the fully loaded
concrete-and-steel cask could not have ended up in the
spent fuel pool because there were mechanical controls
in place to keep it from doing that.
Williams
said the safety stops were in place on May
12.
Both NRC spokesman Neil Sheehan and Stephen
Wark, spokesman for the Vermont Department of Public
Service, said Thursday they didn't have enough
information about the problem but would have more
information today.
Contact Susan Smallheer at susan.smallheer@rutlandherald.com.
|