SS: all Return to New England
Coalition Home Page
COMMENT:
This is another “Rob Williams Says” story; Rob Williams being an
Entergy Nuclear
Consultant to
- END COMMENT -
November 11,
2008
Entergy Nuclear announced Monday the plant had successfully completed a
three-week refueling and maintenance shutdown, and Vermont Yankee was back
generating electricity. Half of the plant's production is sold to
Robert Williams, Entergy Nuclear spokesman, said the discovery of the 16 additional
cracks brings the total number in the steam dryer to 63 cracks.
Williams said the new cracks were a result of improved screening and high-tech
evaluation. He said the company believed the 16 additional cracks were not new,
but that technology was better at detecting them.
"Engineers added 16 additional ones to the steam dryer database this time.
This was from a total of 466 individual inspections on the dryer. The
inspections this time were more precise because they were done with a new, more
stable camera platform," Williams said.
All the cracks were due to intergranular stress
corrosion cracking, a result of aging, he said.
"That means they have likely been present since early in the plant's
operating life. IGSCC is well understood process: it is due to the relief of
metal stress first induced by the heat of the original weld process," he
said.
Williams said the company had said there were 75 cracks in 2007, but improved
inspection equipment, and engineering re-evaluation had lowered the number.
"None have grown," he said.
The inspection is required by NRC in the post uprate
outages to check for similar problems that some other boiling water reactors
experienced after an uprate in structural welds.
"We didn't find any such problems in our welds," he said. Entergy
Nuclear increased power production at Vermont Yankee by 20 percent in March
2006.
Despite the additional cracks, Williams said the steam dryer was in
"good" condition.
At the
The steam dryer, which is made of steel, removes water
from the steam before it heads into the turbines.
Williams refused to say how much money Entergy had spent on the nuclear fuel
and the maintenance work on the reactor, calling it "proprietary"
information
But he said the expense of the outage is paid by Entergy Nuclear. Before
Entergy Nuclear bought the plant in 2002, such costs were passed on to electric
consumers, he said.
One-third of the nuclear fuel in the reactor core was replaced, and the other
two-thirds were rearranged to maximize power production, he said. The old fuel
that was removed from the reactor was placed in the spent fuel pool.
Williams said work was continuing on the cooling towers at Vermont Yankee and
would continue through the winter and spring. The plant's two cooling towers
have had repeated structural problems in the past 15 months due to rot and
insufficient engineering analysis and repair work.
Contact
Return to New